CONSTRUCTION HUB

January 2026 Project Updates: Major Ongoing Construction Projects Across Rwanda

Rwanda’s construction sector maintained strong momentum in January 2026, with major projects across the health, water, energy, transport, sanitation, and real estate sectors recording measurable progress. As reported in February 2026, the updates below reflect project implementation status as of January 2026, highlighting ongoing investments that continue to strengthen public services, improve connectivity, and support national economic growth.

Health Infrastructure Projects

  1. Nyamata Maternity Ward in Bugesera District 

On 21 January 2026, the Rwanda Housing Authority reported that the new maternity ward at Nyamata Hospital had reached 80.49% completion.

Funded by the Imbuto Foundation at a cost of Rwf 6 billion, the project began in 2023 and will nearly double maternity bed capacity. The facility will include:

  • 120 beds for mothers
  • 60 incubator beds
  • An outpatient section

2. Rehabilitation and expansion works at Ngarama Hospital

Rehabilitation and expansion works at Ngarama Hospital continue to advance steadily.

According to updates from Gatsibo District, Phase 1 has been completed, while Phase 2 is currently under construction. The ongoing works include a new multi-storey hospital block, with active formwork, scaffolding, and masonry works underway to expand healthcare capacity.

3. Construction works for the Nyarubuye Medicalized Health Center

Construction of the Nyarubuye Medicalized Health Center is progressing, with reinforced concrete columns erected and structural works taking shape across the site.

Valued at over Rwf 6 billion, the project has completed foundation works and is moving into vertical construction, which will significantly enhance healthcare service delivery in the area once operational.

Water and Sanitation Projects

4. Rehabilitation and extension of eight water supply systems in Nyabihu District

On 21 January 2026, WASAC announced that rehabilitation and extension works on eight water supply systems in Nyabihu District had reached 91% completion.

Implemented under the Stunting Prevention and Reduction Project (SPRP) and funded by the World Bank through RBC, the project will provide clean water to over 39,000 residents in the sectors of Rambura, Jenda, Mulinga, Jomba, and Shyira.

Covering a 94-kilometre network, the works include:

  • Upgrading old systems
  • Expanding pipelines
  • Protecting water sources
  • Constructing reservoirs and water points

Completed systems such as Birembo and Nyiragikokora–Sukiro are already supplying water to communities, schools, and health facilities, with no household now walking more than 500 metres to fetch water.

5. Muhazi Water Treatment Plant

As of 20 January 2026, the Muhazi Water Treatment Plant was reported to be 92% complete.

In its first phase, the plant will supply clean water to 543,397 residents, including communities in Gatsibo and Kayonza districts. The project includes:

  • 256 kilometres of water pipelines
  • 11 water reservoirs with 7,100 cubic metres storage capacity

Located along Lake Muhazi in Murambi Sector, the facility will significantly expand access to safe water across multiple sectors in both districts

6. Mutobo Water Treatment Plant – Musanze District

In January 2026, construction works to expand and upgrade the Mutobo Water Treatment Plant in Busogo Sector, Musanze District were ongoing. Once completed, the plant’s treatment capacity will increase significantly from 12,500 cubic metres per day to 55,500 cubic metres per day. The project is designed as a long-term solution to water supply challenges, increasing the availability of clean and safe water for residents of Musanze and Burera districts, as well as selected sectors in Nyabihu and Rubavu districts.

7. Construction of the Musanze Faecal sludge treatment plant

Construction of the Faecal sludge treatment plant in Musanze reached 71% progress by 30 January 2026, according to MININFRA.

The facility will introduce modern wastewater management solutions, improving sanitation services, environmental protection, and public health outcomes in Musanze and surrounding areas.

8. Faecal Sludge Treatment Plant and Landfill Project – Rubavu District

In January 2026, construction works continued on the Faecal Sludge Treatment Plant and Landfill Project in Rubavu District, a major sanitation infrastructure initiative aimed at improving waste management systems.

Once completed, the facility will enhance sanitation services, protect public health, and support environmentally sustainable waste treatment and disposal for Rubavu District and surrounding areas. The project forms part of broader efforts to strengthen urban sanitation infrastructure and improve living conditions in fast-growing urban centres.

9. Muvumba Multipurpose Dam

Construction of the Muvumba Multipurpose Dam across Rukomo, Gatunda, and Karama sectors reached 44.17% completion in January 2026.

Spanning 796 hectares and costing approximately €124 million (over Rwf 211 billion), the project began in 2022 and is expected to deliver major socio-economic benefits, including:

  • Irrigation for 10,000 hectares of farmland
  • 1 MW hydropower generation
  • 50,000 cubic metres of clean water daily

The project is financed primarily by the African Development Bank and the Government of Rwanda, with full completion scheduled for November 2026.

10. Construction of the Gishanda Dam

Construction of the Gishanda Dam in Kabare Sector had reached 20% completion by 29 January 2026.

Once completed, the dam will provide large-scale irrigation water to farming communities in Kabare and Rwinkwavu, boosting agricultural productivity and food security.

Energy Infrastructure Projects

11. Extension works at Gabiro Substation

REG announced that extension works at Gabiro Substation, together with the construction of the 110 kV transmission line linking Gabiro to the new Nyagatare Substation, had reached 70% completion.

Once completed, the project will strengthen electricity transmission capacity in Eastern Province, improve power reliability, and support growing industrial and residential demand.

12. Bugesera Substation

On 15 January 2026, Rwanda Energy Group (REG) management inspected the Bugesera Substation, which has reached 30% completion. Once completed, the substation is expected to play a key role in stabilizing power supply and improving electricity reliability in Bugesera District.

13. Construction of the 5.2 MW solar power plant in Rwinkwavu

On 29 January 2026, Kayonza District reported that construction of the 5.2 MW solar power plant in Rwinkwavu had reached 90% completion. The facility is being developed to supply reliable electricity to the BioNTech vaccine manufacturing plant.

Transport Infrastructure Projects

14. Base–Butaro–Kidaho road project

As of January 2026, works on the 63-kilometre Base–Butaro–Kidaho road corridor were progressing well.

The Kidaho–Butaro section has already been opened to traffic, with final finishing works underway. The full project is expected to be completed by the end of 2026, significantly improving transport connectivity and economic activity across Burera District.

15. Nyagisozi–Remera–Nshili Border Asphalt Road (18 km)

The Rwf 16+ billion road project is progressing, aiming to boost trade and local mobility. Authorities have called for faster payment of compensation to affected residents to avoid delays and ensure smooth implementation. The project started on 5 June 2025 and is expected to be completed by 5 December 2026

Housing and Real Estate Projects

16. Royal Golf View Apartment Hotel

Construction at the Royal Golf View Apartment Hotel continued steadily through January, with work now firmly in the final phase. Finishing activities are progressing across the project, and all key milestones remain aligned with the planned June 2026 completion, as confirmed in the 18 January 2026 update from DND Developers.

17. Construction works for housing to resettle families affected by the development of the Rusumo Hydropower Plant

Construction of resettlement houses for families affected by the Rusumo Hydropower Plant is nearly complete, with handover expected in early 2026. The project supports 80 families and includes essential infrastructure such as an ECD center and livestock shelters, with over US$4.2 million allocated for housing and related facilities.

As of January 2026, Rwanda’s ongoing construction projects continued to register steady progress across key sectors, reflecting sustained investment in public services, energy security, urban development, and regional connectivity. While several projects are approaching completion, continued coordination, timely financing, and effective implementation will be essential to maintaining momentum as works advance through 2026.


Need Construction Tools?

Looking for reliable hardware at unbeatable prices? From power tools to industrial machinery, Garasi Hardware Ltd has you covered. Visit them in Gisozi, Copcom House — or call +250 795 432 350Affordable Prices Guaranteed. : Garasi Hardware | CONSTRUCTION HUB

Need contractors to support your construction or renovation project?

Explore trusted professionals ready to help you build, upgrade, or transform your space.

Click here to view the full list of building contractors in our directory


We post daily updates on all our social media pages!

Click the link and follow us to stay updated: FOLLOW US

Related Post